Taken from the roll call in the town’s own minutes. The minutes record who was not there and almost never why.
What was decided (2 motions)
2 carried, 0 recorded otherwise. Every motion below is printed as the minutes print it.
THAT PW 18-07, Prudhommes Watermain Upgrade Design - Project Award be received as information; 2 AND THAT that the firm of GHD Limited (GHD) be retained to provide engineering design services at a cost of $140,928 (excluding HST); 3 AND THAT the Mayor and Clerk be authorized to sign and seal the contract documents on behalf of the municipality.
Moved by Councillor P. MacPherson, seconded by Mayor S. Easton
Carried
THAT PW 18-08, Red Maple Avenue, Bridgeport Drive and Queen Victoria Urbanization Design - Project Award be received as information; 2. AND THAT that the firm of UEM be retained to provide engineering design services at a cost of $56,792 (excluding HST); 3. AND THAT the Mayor and Clerk be authorized to sign and sealthe contract documents on behalf of the municipality.
Moved by Mayor S. Easton, seconded by Councillor P. MacPherson